Want to apply for a Lesco new connection but are not sure about the process? You are in the right place! Whether you’re a new homeowner or need an additional connection, navigating the LESCO application process can be confusing. This guide will walk you through everything from demand notice charges to meter connection fees, ensuring a smooth and hassle-free experience. Stay tuned to learn about the new LESCO connection online and find out about demand notice fees, status, and the new meter connection.
How to Apply For Lesco New Connection?
Applying for a Lesco new connection can seem daunting, but with this comprehensive guide, you’ll find the process straightforward and manageable. Whether you’re moving into a new home or need an additional connection, follow these detailed steps to ensure a smooth application process.
Step-by-Step Procedure for Applying for a New Lesco Connection:
Visit the ENC Portal: Start by visiting the Electricity New Connection (b) portal here. This centralized web portal simplifies the application process by allowing you to apply online.
Prepare Required Documents:
Gather and scan the following documents before starting your application:
- Proof of property ownership (e.g., Fard, Registry, or Allotment Letter)
- Attested copies of your CNIC and those of two witnesses (if applying for a single-phase connection, witness copies are not required)
- No Objection Certificate (NOC) if you are a tenant
- A recent electricity bill from a neighbor
- Power of Attorney if the property has multiple owners
- Contractor’s Wiring Test Report
Fill Out the Online Application Form:
- Access the application form on the ENC portal.
- Select LESCO from the list of distribution companies.
- Enter your personal information and connection details, including the type of connection (Domestic, Commercial, etc.), your CNIC number, and your contact details.
- Upload the scanned copies of the required documents.
Submit the Application:
- Review your application to ensure all information is accurate.
- Agree to the terms and conditions.
- Apply and print a copy for your records.
- Attach the printed application form and all documents, then submit them to the nearest LESCO office.
Receive and Pay the Demand Notice:
- After LESCO verifies your documents, you will receive a demand notice.
- Pay the amount specified in the demand notice at the designated bank.
- Submit the payment receipt along with a copy of the demand notice to the LESCO office.
Connection Installation:
- Once LESCO verifies your payment, the installation of your new meter connection will be scheduled.
- You will receive notification of the installation date.
Estimated time for Lesco New Meter Connection:
Wondering how long it will take to get your new LESCO meter connection? The estimated time varies depending on the connection category, which is determined by the load requirements. LESCO categorizes connections into three main types, each with its own timeline:
Category 1: Up to 15 kW
For connections up to 15 kW, the process is typically completed within 30 days. Here’s a breakdown of the steps and the estimated time for each:
- Application Submission: 1 Day
- Submit your application form with the required documents at the nearest LESCO office. You’ll receive a receipt and a seniority number.
- Site Inspection: 3 Days
- A LESCO officer will visit the site to verify the feasibility of the new connection.
- Cost Estimation: 2 Days
- If the site is approved, the office will calculate the estimated cost for the connection.
- Demand Notice Issuance: 2 Days
- A demand notice will be issued, either for pickup or sent by post.
- Fee Payment and Submission: 2 Days
- Pay the demand notice fee at a designated bank and submit the receipt to LESCO.
- Wiring Test Report Submission: 3 Days
- Submit your wiring test report, which will then be verified by LESCO.
- Priority Listing: 1 Day
- Applicants are prioritized based on the date they submitted their dues.
- Service Connection Order: 3 Days
- A service connection order is issued once the above steps are complete.
- Equipment Procurement: 8 Days
- LESCO will request and receive the necessary connection items like meters and installation kits from their store.
- Meter Installation: 5 Days
- The SDO or Assistant Manager Operations will install your new meter.
Total Estimated Time: 30 Days
Category 2: 16 to 70 kW / 400 Volts
For this category, the process is similar to Category 1 but can take up to 44 days due to the higher load requirements and additional verification steps.
Category 3: 71 to 500 kW / 400 Volts
For the highest load category, the process involves the same steps but may extend up to 73 days from application submission to meter installation.
What is Lesco New Connection Fee?
To get the exact fee for a new LESCO connection, it’s best to contact the concerned LESCO office directly. The fee can vary depending on factors like the connection type and load requirements. However, for an estimate, the new connection fee is approximately Rs 7,240. Keep in mind that this is just an estimate, and you should reach out to LESCO for the most accurate and up-to-date information.
How to Check LESCO New Connection Status in 2024?
To check the status of your LESCO new connection application, you will need to contact the concerned officer at the relevant LESCO office. They can provide you with the most current information about your application and any next steps you may need to take.
What is Lesco Demand Notice?
A Lesco Demand Notice is a formal document issued by LESCO (part of WAPDA) that specifies the charges an applicant must pay to secure a new electricity connection. This notice outlines the cost details and instructs the applicant to submit the required payment at a designated bank.
What Is Lesco Demand Notice Fee?
Single-Phase Meter:
The fee for a single-phase meter is Rs. 10,500 for a domestic connection.
Three-Phase Connection:
The price for a three-phase connection ranges from Rs. 33,500 to Rs. 235,000, depending on various factors such as load requirements and specific installation needs.
Conclusion:
Applying for a LESCO new connection doesn’t have to be a daunting task. By following this comprehensive guide, you’ll be equipped with all the necessary information to navigate the process smoothly. From understanding the Demand Notice charges to preparing the required documents and knowing the timelines, this guide ensures you can manage each step efficiently.
FAQs
How can I apply for a LESCO new connection?
You can apply for a LESCO new connection by visiting the Electricity New Connection (ENC) portal and following the step-by-step procedure.
What documents are required for a LESCO new connection?
Required documents include proof of property ownership, attested copies of CNIC, a No Objection Certificate if you're a tenant, a recent neighbor’s electricity bill, a Power of Attorney if needed, and a Contractor’s Wiring Test Report.
How do I submit the LESCO new connection application?
Submit your completed application form along with the required documents to the nearest LESCO office after applying online.
What are the charges for a LESCO single-phase meter?
The fee for a single-phase meter for a domestic connection is Rs. 10,500.
How much does a LESCO three-phase connection cost?
The price for a three-phase connection ranges from Rs. 33,500 to Rs. 235,000 depending on the load requirements.
How long does it take to get a LESCO new meter connection?
The estimated time for a LESCO new meter connection ranges from 30 days to 73 days, depending on the connection category and load requirements.
What is a LESCO Demand Notice?
A LESCO Demand Notice is a formal document specifying the charges an applicant must pay to secure a new electricity connection.
How can I check the status of my LESCO new connection application in 2024?
To check the status, contact the relevant officer at your local LESCO office for the most current information.
What should I do after receiving the LESCO Demand Notice?
Pay the specified amount at the designated bank and submit the payment receipt along with a copy of the demand notice to the LESCO office.